We are working towards countertop install late next week.
Electrical trim out has begun.
Plumbing trim is ready for install as soon as tops are installed.
Stone threshold are installed. We will be pouring the tabby porches next week.
Bricking the garden walls will be complete early next week.
Hardscapes will begin next week.
The Riceland Way fountain has been delivered and installation will follow.
Sottile has hand selected the Oak Trees for Silk Hope Drive and Riceland Way. Installation will come in 2 deliveries next week on Tuesday and Thursday.
Undercutting for the Riceland pavers that go behind the curb is complete. Pavers will be delivered next week and installation of same will follow.
The Riceland Way gas street lanterns have been delivered. Installation will commence in the following week.
We are working on the layout of the fire pit area. Submittal to the ARB will be next week.
Filling and compaction of the lot 50 and the alley is planned to start late next week.