The planter boxes are completed and all the post have been set around the perimeter. The post for the Barn have been set and the floor has been poured and prepped for brick. The lining has been installed in all the boxes. We will lay out the well location first of the week to get…
This week we re-Hydroseedes the entire site. We have put up a erosion control barriers over the rear entrance and Hydroseedes that area for grass.
This week we continued and nearly completed the first floor framing. The second floor material package is due to arrive Monday and we will begin framing the second floor next week. This sequencing should set up nicely for the electrical mechanical and plumbing subcontractors to move into this house once they’re done with 47. Next…
This week we continued working on the plumbing electrical and HVAC rough in’s. The exterior trim package arrived and will start Monday. The roofing material has also arrived and we will be seeking approval from the ARB next week on the mock up. The masonry has arrived on site and we will begin masonry in…
Lot corner markers are being made and will be installed in a few weeks. Misc site prep and maintenance is on going and we plan to edge the roadways later next week.
Construction began on the retainage wall at the rear of the farm, The first and second row of planter box reinforcement was installed. We also installed and graded the area to raise the beds. Next week we will continue the framing and grading.
This week we completed the foundation preparation, passed inspections, and poured the slab. The framing material package is set to arrive next week and we will begin laying out the walls for the first floor.
This week we finished the plumbing rough in and completed the design of the HVAC system. The HVAC system has been ordered and we will begin rough in installation next week. We met the lighting designers onsite this again this week to finalize the order. The electrical rough in will begin towards the end of…
Some of the dirt from lots 47 and 48 will be reused to extend and build the fire mound which will be located behind these lots. We have authorized the supply and installation of brand new corner markers throughout Silk Hope.
We are working on finalizing some of the structural details within the pavilion.
The area has been cleared and Ford is currently removing the existing farm. The new well installation is schedule for 2 weeks from today. We will begin construction on the new farm later next week
The blockwork was completed this week and we began the plumbing rough in underground. Next week we will finish the underground work and prep to pour the slab.
Lot 47 This week we continued the framing punch list and the plumbing rough in. The house was wrapped, copper window pans installed, and the additional flashing for the windows and corners was installed. Next week we will continue the plumbing rough in and finalize the HVAC layout and equipment. Chris, Jeff and I are…